Our quality checklist

234 checks on every home. Each one signed.

From the land documents to the first monsoon after you move in, your home passes 234 checks across ten gates. Here is every single one: what’s checked, the standard it follows and who signs it.

  • 90hold points, where work stops until signed
  • 32tests, on site and at accredited labs
  • 10gates, each signed by your client manager
  • +48more checks when we do your interiors
Ten gates

Where the checks happen.

Most checks sit where problems hide: the structure, then everything that disappears inside walls and floors. Tap a gate to see its checks.

Ten gates, G0 to G9, plus aftercare visits in the first year.

How to read a check

Five kinds of check. Named people signing.

Every check on the list has a type and a person who signs it. Hold points are the strictest: nothing on site moves until they’re signed.

Type of check

  • Hold107

    Work stops. Nothing moves on until this is checked and signed.

  • Witness17

    Done in front of you, or with you invited to see it.

  • Test38

    Measured or tested, on site or at an accredited lab, with the result recorded.

  • Review93

    Documents, drawings or records checked and signed.

  • Spot check27

    Checked on site by surprise, as the work goes on.

Who signs

  • Site engineer

    Runs your site day to day and checks the work as it happens.

  • Quality engineer

    Reports to the office, not the site team, and signs the hold points.

  • Design lead

    Checks the brief, drawings and specification.

  • Client manager

    Your one point of contact at Build 1. Signs every gate, on the quality team’s records.

  • NABL lab

    An accredited lab tests samples. Results go into your record.

  • Client manager + you

    Some checks need your signature too.

The full list

Every check, gate by gate.

Search the list, or filter by type. Codes like ST-24 are how the check appears in your project record.

G0LandBefore you commit to the plot12checks

Documents

  • LD-01
    Title deed

    Ownership and the chain of title match the seller and the survey number.

    StandardRevenue recordsTypeReviewSigned byClient manager
  • LD-02
    Encumbrance certificate

    No mortgage, lien or claim on the land for the period checked.

    StandardRegistration recordsTypeReviewSigned byClient manager
  • LD-03
    Land tax receipt

    Basic tax paid up to date in the owner’s name.

    StandardVillage recordsTypeReviewSigned byDesign lead
  • LD-04
    Possession and location sketch

    Possession certificate and village location sketch match the plot on the ground.

    StandardVillage recordsTypeReviewSigned byDesign lead

Restrictions

  • LD-05
    Paddy and wetland data bank

    Plot is not listed in the data bank, or the RDO order allowing a house is in hand.

    StandardKerala Paddy Land and Wetland Act 2008TypeReviewSigned byClient manager
  • LD-06
    Coastal, flood and airport zones

    CRZ map, 2018 flood levels and airport height zoning checked where they apply.

    StandardCRZ 2019, AAI CCZMTypeReviewSigned byDesign lead
  • LD-07
    Road width and setbacks

    Access road width and the setbacks it triggers checked against the building rules.

    StandardKMBR / KPBR 2019TypeReviewSigned byDesign lead

Site

  • LD-08
    Boundary and plot size

    Boundary stones located and plot dimensions measured against the documents.

    StandardSurvey sketchTypeHoldSigned bySite engineer
  • LD-09
    Levels survey

    Spot levels taken across the plot and the road to plan the plinth and drainage.

    StandardSite surveyTypeHoldSigned bySite engineer
  • LD-10
    Existing features

    Trees, wells, structures, power lines and drains on and around the plot recorded.

    StandardSite recordTypeReviewSigned bySite engineer
  • LD-11
    Neighbouring buildings

    Condition of neighbouring walls and buildings photographed before work starts.

    StandardPhoto recordTypeReviewSigned bySite engineer
  • LD-12
    Soil investigation planned

    Number and depth of boreholes or trial pits fixed for the soil test.

    StandardIS 1892TypeReviewSigned byDesign lead
G1BriefYour needs, written down8checks

Brief

  • BR-01
    Family needs

    Rooms, ages, routines and future plans recorded in one brief.

    StandardBuild 1 brief formTypeReviewSigned byDesign lead
  • BR-02
    Budget and package

    Budget range and the chosen package recorded, with what each includes.

    StandardPackage specificationTypeReviewSigned byDesign lead
  • BR-03
    Style and preferences

    Style, materials and vastu preferences recorded with reference images.

    StandardStyle discoveryTypeReviewSigned byDesign lead
  • BR-04
    Plot fit

    The brief checked against plot size, setbacks and the soil and level findings.

    StandardKMBR / KPBR 2019TypeReviewSigned byDesign lead
  • BR-05
    Systems wish list

    Solar, CCTV, smart home and other systems noted so they’re designed in early.

    StandardBuild 1 brief formTypeReviewSigned byDesign lead
  • BR-06
    Communication plan

    How and when you get updates, and who else in the family gets access.

    StandardBuild 1 brief formTypeReviewSigned byDesign lead
  • BR-07
    Timeline

    Target start and move-in dates recorded, with monsoon timing considered.

    StandardBuild 1 brief formTypeReviewSigned byDesign lead
  • BR-08
    Brief sign-off

    You approve the written brief before design starts.

    StandardBuild 1 brief formTypeWitnessSigned byClient manager + you
G2OfferEngineered, then priced18checks

Soil and structure

  • DS-01
    Soil test

    Bearing capacity and soil type tested at an accredited lab.

    StandardIS 2131 / IS 1888TypeTestSigned byNABL lab
  • DS-02
    Foundation design

    Foundation type and depth designed from the soil report.

    StandardIS 1904 / IS 6403TypeReviewSigned byDesign lead
  • DS-03
    Structural design

    Frame, slabs and beams designed for loads and earthquake zone.

    StandardIS 456 / IS 875 / IS 1893TypeReviewSigned byDesign lead
  • DS-04
    Independent structural review

    A second engineer checks the structural drawings before release.

    StandardIS 456TypeReviewSigned byClient manager

Drawings

  • DS-05
    Plan against building rules

    Setbacks, coverage, floor area and height checked against the rules.

    StandardKMBR / KPBR 2019TypeReviewSigned byDesign lead
  • DS-06
    Room sizes and ventilation

    Habitable rooms, kitchens and toilets meet minimum size, light and ventilation.

    StandardKMBR / KPBR 2019, NBC 2016TypeReviewSigned byDesign lead
  • DS-07
    Staircase and railings

    Riser, tread, width and railing height meet the code.

    StandardNBC 2016 Part 4TypeReviewSigned byDesign lead
  • DS-08
    Door and window schedule

    Every opening sized and listed with its frame, shutter and glass.

    StandardDrawing scheduleTypeReviewSigned byDesign lead
  • DS-09
    Services layout

    Plumbing, drainage and electrical layouts coordinated with the structure.

    StandardNBC 2016 Parts 8 and 9TypeReviewSigned byDesign lead
  • DS-10
    Rainwater and site drainage

    Roof outlets, yard drainage and rainwater harvesting designed.

    StandardIS 15797, KMBRTypeReviewSigned byDesign lead
  • DS-11
    Septic tank and well distance

    Septic tank and soak pit sized and placed at the required distance from wells.

    StandardIS 2470, KMBRTypeReviewSigned byDesign lead

Offer

  • DS-12
    BOQ quantities

    Quantities taken off the drawings and cross-checked by a second person.

    StandardIS 1200TypeReviewSigned byClient manager
  • DS-13
    Specification schedule

    Every material named with brand, grade and finish.

    StandardPackage specificationTypeReviewSigned byDesign lead
  • DS-14
    Allowances and exclusions

    Allowance items and exclusions listed clearly in the offer.

    StandardBuild 1 offerTypeReviewSigned byClient manager
  • DS-15
    Programme

    A dated programme, stage by stage, with monsoon allowance.

    StandardBuild 1 programmeTypeReviewSigned byClient manager
  • DS-16
    Payment schedule

    Payments linked to finished, checked stages.

    StandardBuild 1 offerTypeReviewSigned byClient manager
  • DS-17
    Permit drawings

    Permit set prepared and signed by a licensed engineer.

    StandardKMBR / KPBR 2019TypeReviewSigned byDesign lead
  • DS-18
    Offer review

    Your client manager reviews price, scope and programme before you see it.

    StandardBuild 1 offerTypeReviewSigned byClient manager
G3ContractEverything in writing8checks

Agreement

  • CT-01
    Agreement signed

    Agreement signed with all annexures attached.

    StandardIndian Contract ActTypeWitnessSigned byClient manager + you
  • CT-02
    Drawings annexed

    Approved drawings listed by number and revision.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • CT-03
    Specification annexed

    The specification schedule attached and initialled.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • CT-04
    BOQ and price

    Itemised BOQ and the fixed price attached.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • CT-05
    Programme and on-time promise

    Dated programme and the on-time promise written in.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • CT-06
    Warranty terms

    Structural, waterproofing and defects warranty written in.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • CT-07
    Variation procedure

    How changes are priced and approved before work, in writing.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • CT-08
    Update channel set up

    Daily photo updates and family access set up for you.

    StandardBuild 1 agreementTypeReviewSigned bySite engineer
G4Ready for siteNothing starts half-ready16checks

Approvals

  • RS-01
    Building permit

    Permit issued by the local body and its conditions noted.

    StandardKMBR / KPBR 2019TypeReviewSigned byClient manager
  • RS-02
    Construction drawings released

    Good-for-construction drawings stamped and issued to site.

    StandardBuild 1 drawing registerTypeReviewSigned byDesign lead
  • RS-03
    Drawing coordination check

    Architecture, structure and services drawings checked for clashes.

    StandardBuild 1 drawing registerTypeReviewSigned byDesign lead

Materials

  • RS-04
    Material submittals

    Cement, steel, blocks, pipes and wires approved by brand and grade.

    StandardIS 269, IS 1786, IS 2185TypeReviewSigned byQuality engineer
  • RS-05
    Sample board

    Tiles, paints and fittings approved by you on a physical sample board.

    StandardPackage specificationTypeWitnessSigned byClient manager + you
  • RS-06
    Concrete mix design

    Mix designed for the grade, or the ready-mix supplier approved.

    StandardIS 10262 / IS 4926TypeReviewSigned byQuality engineer
  • RS-07
    Lab tie-up

    NABL-accredited lab booked for cube, steel and material tests.

    StandardNABLTypeReviewSigned byQuality engineer
  • RS-08
    Long-lead items ordered

    Windows, steel and other long-lead items ordered on time.

    StandardBuild 1 programmeTypeReviewSigned bySite engineer

Team

  • RS-09
    Crew assigned

    Site engineer, supervisor and trade teams assigned and named.

    StandardBuild 1 programmeTypeReviewSigned byClient manager
  • RS-10
    Quality briefing

    Subcontractors briefed on the checks for their work.

    StandardBuild 1 quality planTypeReviewSigned byQuality engineer
  • RS-11
    Baseline programme frozen

    Programme frozen as the baseline for tracking delay.

    StandardBuild 1 programmeTypeReviewSigned byClient manager
  • RS-12
    BOQ frozen

    BOQ frozen so every later change is a written variation.

    StandardBuild 1 BOQTypeReviewSigned byClient manager

Site plan

  • RS-13
    Safety plan

    Site safety plan, permits-to-work and emergency contacts ready.

    StandardNBC 2016 Part 7TypeReviewSigned byQuality engineer
  • RS-14
    Site logistics

    Storage, access, water and power for construction planned.

    StandardBuild 1 site planTypeReviewSigned bySite engineer
  • RS-15
    Construction water and power

    Temporary water and electricity connections arranged.

    StandardBuild 1 site planTypeReviewSigned bySite engineer
  • RS-16
    Ready-for-site sign-off

    Your client manager confirms the site is ready to start.

    StandardBuild 1 gate recordTypeHoldSigned byClient manager
G5MobiliseSet out right, from day one18checks

Handover of site

  • MB-01
    Site condition record

    Plot and boundaries photographed and recorded at handover.

    StandardPhoto recordTypeReviewSigned bySite engineer
  • MB-02
    Site fencing and signage

    Site fenced, gated and signed; public kept safe.

    StandardNBC 2016 Part 7TypeSpot checkSigned bySite engineer

Set-out

  • MB-03
    Benchmark

    A fixed benchmark set and protected for all levels.

    StandardBuild 1 set-out recordTypeHoldSigned bySite engineer
  • MB-04
    Centre-line set-out

    Building lines set out from the drawings and checked by a second person.

    StandardBuild 1 set-out recordTypeHoldSigned byQuality engineer
  • MB-05
    Diagonals and squareness

    Diagonals measured to confirm the layout is square.

    StandardBuild 1 set-out recordTypeHoldSigned byQuality engineer
  • MB-06
    Setbacks on the ground

    Setbacks from boundaries measured against the permit drawing.

    StandardKMBR / KPBR 2019TypeHoldSigned bySite engineer
  • MB-07
    Plinth and floor levels

    Plinth and finished floor levels fixed from the benchmark.

    StandardBuild 1 set-out recordTypeHoldSigned bySite engineer

Safety

  • MB-08
    Safety induction and PPE

    Every worker inducted and given a helmet, shoes and gloves.

    StandardIS 2925, NBC 2016 Part 7TypeSpot checkSigned byQuality engineer
  • MB-09
    First aid and emergency plan

    First-aid kit on site and emergency numbers displayed.

    StandardNBC 2016 Part 7TypeSpot checkSigned byQuality engineer
  • MB-10
    Excavation safety

    Trench sides sloped or shored; edges barricaded.

    StandardIS 3764TypeHoldSigned bySite engineer

Materials on site

  • MB-11
    Cement storage

    Cement stored on a raised, dry platform and used first-in, first-out.

    StandardIS 4082TypeSpot checkSigned bySite engineer
  • MB-12
    Cement batch check

    Brand, grade and date of manufacture checked on every delivery.

    StandardIS 269 / IS 1489TypeReviewSigned byQuality engineer
  • MB-13
    Steel mill certificates

    Every steel lot matched to its mill certificate and tag.

    StandardIS 1786TypeReviewSigned byQuality engineer
  • MB-14
    Steel tensile test

    Steel samples tested at the lab for strength and elongation.

    StandardIS 1786 / IS 1608TypeTestSigned byNABL lab
  • MB-15
    Sand silt test

    Silt content of sand checked on site before use.

    StandardIS 2386 / IS 383TypeTestSigned bySite engineer
  • MB-16
    Aggregate grading

    Coarse aggregate size and grading checked.

    StandardIS 383 / IS 2386TypeTestSigned byQuality engineer
  • MB-17
    Water quality

    Construction water tested for suitability.

    StandardIS 456 cl 5.4 / IS 3025TypeTestSigned byNABL lab
  • MB-18
    Block or brick test

    Strength, size and water absorption tested on samples.

    StandardIS 2185 / IS 3495TypeTestSigned byNABL lab
G6StructureFoundation to roof slab43checks

Foundation

  • ST-01
    Excavation depth and size

    Pit or trench depth, width and level checked against the drawing.

    StandardStructural drawingTypeHoldSigned bySite engineer
  • ST-02
    Founding strata

    Engineer inspects the soil at founding level before PCC.

    StandardIS 1904TypeHoldSigned byQuality engineer
  • ST-03
    Dewatering

    Pits kept dry; no concrete placed in standing water.

    StandardIS 456TypeSpot checkSigned bySite engineer
  • ST-04
    Anti-termite treatment

    Soil treated with approved chemical at the right dose before PCC.

    StandardIS 6313 Part 2TypeWitnessSigned byQuality engineer
  • ST-05
    PCC bed

    Levelling concrete laid to thickness and level.

    StandardIS 456TypeHoldSigned bySite engineer
  • ST-06
    Footing reinforcement

    Bar size, spacing and cover in footings checked.

    StandardIS 456 / IS 2502TypeHoldSigned byQuality engineer
  • ST-07
    Column starter bars

    Starter bars positioned and held to the column grid.

    StandardStructural drawingTypeHoldSigned byQuality engineer
  • ST-08
    Stone or laterite foundation

    Masonry foundation bond, mortar and through-stones checked, where used.

    StandardIS 1597 / IS 3620TypeHoldSigned bySite engineer
  • ST-09
    Backfilling

    Backfill placed in layers, watered and compacted.

    StandardIS 456TypeSpot checkSigned bySite engineer

Plinth

  • ST-10
    Plinth beam reinforcement

    Bars, stirrups and laps in plinth beams checked.

    StandardIS 456 / IS 2502TypeHoldSigned byQuality engineer
  • ST-11
    Plinth level

    Top of plinth checked against the benchmark.

    StandardBuild 1 set-out recordTypeHoldSigned bySite engineer
  • ST-12
    Damp-proof course

    DPC laid to thickness with waterproofing compound.

    StandardIS 3067 / IS 2645TypeHoldSigned byQuality engineer
  • ST-13
    Plinth filling

    Filling placed in layers, compacted and treated against termites.

    StandardIS 6313 Part 2TypeWitnessSigned bySite engineer

Every pour

  • ST-14
    Formwork line, level and plumb

    Shuttering aligned, levelled, plumbed and propped.

    StandardIS 14687TypeHoldSigned bySite engineer
  • ST-15
    Formwork clean and sealed

    Formwork cleaned, joints sealed and release agent applied.

    StandardIS 14687TypeHoldSigned bySite engineer
  • ST-16
    Bar size and spacing

    Bar diameter and spacing checked against the bar schedule.

    StandardIS 2502TypeHoldSigned byQuality engineer
  • ST-17
    Laps and anchorage

    Lap lengths and anchorage meet the design; laps staggered.

    StandardIS 456 cl 26.2TypeHoldSigned byQuality engineer
  • ST-18
    Cover to steel

    Cover blocks of the right size fixed throughout.

    StandardIS 456 cl 26.4TypeHoldSigned byQuality engineer
  • ST-19
    Chairs and spacers

    Top steel held at the right height with chairs.

    StandardIS 456TypeHoldSigned bySite engineer
  • ST-20
    Embedded services

    Conduits, sleeves and inserts placed and photographed before the pour.

    StandardServices drawingTypeHoldSigned bySite engineer
  • ST-21
    Pre-pour sign-off

    Pre-pour checklist signed and photographed before concrete arrives.

    StandardBuild 1 pour cardTypeHoldSigned byQuality engineer
  • ST-22
    Delivery ticket

    Ready-mix grade, batch time and water-cement ratio checked on the ticket.

    StandardIS 4926TypeReviewSigned bySite engineer
  • ST-23
    Slump test

    Workability tested on arrival or at the mixer.

    StandardIS 1199TypeTestSigned bySite engineer
  • ST-24
    Cube samples

    Cubes taken at the required frequency for every pour.

    StandardIS 456 cl 15.2TypeTestSigned byQuality engineer
  • ST-25
    Compaction

    Concrete vibrated properly; no segregation.

    StandardIS 456 cl 13.3TypeSpot checkSigned bySite engineer
  • ST-26
    Construction joints

    Joints placed only where the engineer approves.

    StandardIS 456 cl 13.4TypeHoldSigned byQuality engineer
  • ST-27
    Curing

    Curing started on time and logged daily for the full period.

    StandardIS 456 cl 13.5TypeSpot checkSigned bySite engineer
  • ST-28
    7-day cube results

    Early strength checked at the lab.

    StandardIS 516TypeTestSigned byNABL lab
  • ST-29
    28-day cube results

    Characteristic strength confirmed at the lab.

    StandardIS 516 / IS 456 cl 16TypeTestSigned byNABL lab
  • ST-30
    Formwork removal

    Props removed only after the minimum striking time.

    StandardIS 456 cl 11.3TypeHoldSigned bySite engineer
  • ST-31
    Surface after stripping

    Honeycombing, cracks and exposed steel inspected and repaired.

    StandardIS 456TypeHoldSigned byQuality engineer

Columns

  • ST-32
    Column reinforcement

    Main bars and ties checked, with closer ties near joints as designed.

    StandardIS 456 / IS 13920TypeHoldSigned byQuality engineer
  • ST-33
    Column size and plumb

    Column size and verticality checked after stripping.

    StandardIS 456TypeHoldSigned bySite engineer

Beams and slabs

  • ST-34
    Beam reinforcement

    Stirrup spacing and extra bars at supports checked.

    StandardIS 456 / IS 2502TypeHoldSigned byQuality engineer
  • ST-35
    Slab reinforcement

    Main, distribution and extra top bars checked.

    StandardIS 456 / IS 2502TypeHoldSigned byQuality engineer
  • ST-36
    Slab thickness and level

    Slab depth and top level checked before and after the pour.

    StandardStructural drawingTypeHoldSigned bySite engineer
  • ST-37
    Sunken slabs

    Wet-area sunk depth checked against the drawing.

    StandardStructural drawingTypeHoldSigned bySite engineer
  • ST-38
    Cantilevers and sunshades

    Top reinforcement in cantilevers and sunshades checked.

    StandardIS 456TypeHoldSigned byQuality engineer
  • ST-39
    Lintels

    Lintel bearing, size and reinforcement checked.

    StandardIS 456TypeHoldSigned bySite engineer
  • ST-40
    Staircase

    Waist, riser and tread checked; reinforcement continuous.

    StandardIS 456, NBC 2016TypeHoldSigned byQuality engineer
  • ST-41
    Roof slope and outlets

    Roof slab falls to outlets; outlets sized and placed.

    StandardStructural drawingTypeHoldSigned bySite engineer
  • ST-42
    Rebound hammer check

    Non-destructive check where any concrete is in doubt.

    StandardIS 13311 Part 2TypeTestSigned byQuality engineer

Gate

  • ST-43
    Structure certificate

    Your client manager signs the structure gate on the quality team’s records.

    StandardBuild 1 gate recordTypeHoldSigned byClient manager
G7Envelope and servicesWalls, pipes, wires, waterproofing45checks

Masonry

  • EN-01
    Mortar mix

    Mortar mixed to the specified ratio and used within its working time.

    StandardIS 2250TypeSpot checkSigned bySite engineer
  • EN-02
    Line, level and plumb

    Walls checked for line, level and plumb as they rise.

    StandardIS 2212 / IS 1905TypeHoldSigned bySite engineer
  • EN-03
    Joint thickness and bond

    Joints even and fully filled; correct bond kept.

    StandardIS 2212TypeSpot checkSigned bySite engineer
  • EN-04
    Wall-to-column ties

    Ties or mesh fixed where walls meet columns.

    StandardIS 1905TypeHoldSigned byQuality engineer
  • EN-05
    Openings

    Door and window openings sized and placed to the schedule.

    StandardDrawing scheduleTypeHoldSigned bySite engineer
  • EN-06
    Laterite masonry

    Laterite blocks sound, dressed and laid to bond, where used.

    StandardIS 3620TypeHoldSigned bySite engineer
  • EN-07
    Masonry curing

    Masonry kept wet for the curing period.

    StandardIS 2212TypeSpot checkSigned bySite engineer

Frames

  • EN-08
    Door and window frames

    Frames fixed square, plumb and level with hold-fasts.

    StandardIS 4021TypeHoldSigned bySite engineer
  • EN-09
    Frame protection

    Frames protected from damage and plaster splashes.

    StandardBuild 1 site practiceTypeSpot checkSigned bySite engineer

Roofing

  • EN-10
    Roof truss

    Truss members, welds and anchorage checked, where used.

    StandardIS 800TypeHoldSigned byQuality engineer
  • EN-11
    Anti-rust treatment

    Steel cleaned and primed before painting.

    StandardIS 2629TypeSpot checkSigned bySite engineer
  • EN-12
    Roof tiles

    Tile quality and fixing, overlap and pointing checked.

    StandardIS 654TypeHoldSigned bySite engineer
  • EN-13
    Gutters and downpipes

    Gutters sloped and downpipes sized to carry Kerala rain.

    StandardIS 15797TypeHoldSigned bySite engineer

Plumbing

  • EN-14
    Pipe material

    Pipes and fittings of the approved brand and ISI grade.

    StandardIS 15778 / IS 4985TypeReviewSigned byQuality engineer
  • EN-15
    Concealed supply lines

    Routes photographed before walls and floors are closed.

    StandardNBC 2016 Part 9TypeHoldSigned bySite engineer
  • EN-16
    Water supply pressure test

    Lines held at test pressure with no drop before concealing.

    StandardIS 2065, NBC 2016 Part 9TypeTestSigned byQuality engineer
  • EN-17
    Drainage slope

    Waste and soil pipes laid to the right fall.

    StandardIS 1742TypeHoldSigned bySite engineer
  • EN-18
    Drainage water test

    Drain lines filled and checked for leaks.

    StandardIS 1742TypeTestSigned byQuality engineer
  • EN-19
    Floor traps

    Trap levels set so floors drain to them.

    StandardIS 1742TypeHoldSigned bySite engineer
  • EN-20
    Sleeves and penetrations

    Pipes through walls and slabs sleeved and sealed.

    StandardNBC 2016 Part 9TypeHoldSigned bySite engineer
  • EN-21
    Tank connections

    Sump and overhead tank inlet, outlet and overflow checked.

    StandardIS 2065TypeHoldSigned bySite engineer

Electrical

  • EN-22
    Conduits and boxes

    Conduits of the right size and grade; boxes fixed level.

    StandardIS 9537TypeReviewSigned bySite engineer
  • EN-23
    Concealed wiring routes

    Conduit routes photographed before plaster.

    StandardIS 732TypeHoldSigned bySite engineer
  • EN-24
    Wire size and colour

    Wire size for each circuit and colour code checked.

    StandardIS 694 / IS 732TypeHoldSigned byQuality engineer
  • EN-25
    Circuits and distribution board

    Circuits separated as designed; MCB and RCCB ratings checked.

    StandardIS 8828 / IS 12640TypeReviewSigned byQuality engineer
  • EN-26
    Earth pits

    Earth pits built and earth resistance measured.

    StandardIS 3043TypeTestSigned byQuality engineer
  • EN-27
    Low-voltage provisions

    TV, data, CCTV and smart-home conduits laid.

    StandardIS 732TypeHoldSigned bySite engineer
  • EN-28
    Solar and backup provision

    Conduits and space for solar, inverter and EV charging provided.

    StandardIS 732TypeHoldSigned bySite engineer
  • EN-29
    Lightning protection

    Air terminals and down conductors installed and tested, where specified.

    StandardIS/IEC 62305TypeTestSigned byQuality engineer

Plaster

  • EN-30
    Surface preparation

    Concrete hacked, surfaces wetted, mesh fixed at joints.

    StandardIS 1661TypeHoldSigned bySite engineer
  • EN-31
    Plaster mix and thickness

    Mix and thickness checked against the specification.

    StandardIS 1661TypeSpot checkSigned bySite engineer
  • EN-32
    Plaster flatness

    Checked with a 2 m straightedge to the package tolerance.

    StandardIS 1661TypeHoldSigned byQuality engineer
  • EN-33
    External plaster

    Waterproofing additive and drip grooves in external plaster.

    StandardIS 1661 / IS 2645TypeHoldSigned bySite engineer
  • EN-34
    Plaster curing

    Plaster cured for the full period.

    StandardIS 1661TypeSpot checkSigned bySite engineer

Waterproofing

  • EN-35
    Substrate preparation

    Surfaces clean, sound and coved at corners before waterproofing.

    StandardIS 3067TypeHoldSigned byQuality engineer
  • EN-36
    Bathroom waterproofing

    Coats applied with upturns on walls around wet areas.

    StandardIS 3067TypeHoldSigned byQuality engineer
  • EN-37
    Bathroom ponding test

    Wet areas flooded and held to check for leaks.

    StandardIS 3067TypeTestSigned byQuality engineer
  • EN-38
    Sunken slab filling

    Sunken slabs filled only after the ponding test is passed.

    StandardIS 3067TypeHoldSigned bySite engineer
  • EN-39
    Terrace waterproofing

    Terrace system laid to specification, with slopes to outlets.

    StandardIS 3067TypeHoldSigned byQuality engineer
  • EN-40
    Terrace ponding test

    Terrace flooded and held to check for leaks.

    StandardIS 3067TypeWitnessSigned byQuality engineer
  • EN-41
    Water tank test

    Tanks filled and checked for leaks.

    StandardIS 3370TypeTestSigned byQuality engineer
  • EN-42
    Parapet and coping

    Parapet tops sloped and sealed to shed water.

    StandardIS 3067TypeHoldSigned bySite engineer
  • EN-43
    Pipe penetrations

    Every pipe through a wet area or terrace sealed.

    StandardIS 3067TypeHoldSigned bySite engineer

Gate

  • EN-44
    Concealment photos

    Everything hidden in walls and floors photographed and shared.

    StandardBuild 1 gate recordTypeWitnessSigned byQuality engineer
  • EN-45
    Envelope and services gate

    Your client manager signs the gate on the quality team’s records.

    StandardBuild 1 gate recordTypeHoldSigned byClient manager
G8FinishesEverything you see and touch46checks

Floors and tiles

  • FN-01
    Tile batch and shade

    Size, shade and batch checked before laying.

    StandardIS 15622TypeReviewSigned byQuality engineer
  • FN-02
    Floor base level

    Base levelled before tiling.

    StandardIS 15622TypeHoldSigned bySite engineer
  • FN-03
    Adhesive or mortar bed

    Correct adhesive or bed, fully covering each tile.

    StandardIS 15477TypeSpot checkSigned bySite engineer
  • FN-04
    Floor level and slope

    Floors level; wet areas slope to the drain.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • FN-05
    Lippage

    Edge height difference between tiles within the package tolerance.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • FN-06
    Joints and grout

    Joint width even; grout full and cleaned.

    StandardIS 15622TypeSpot checkSigned bySite engineer
  • FN-07
    Hollowness tap test

    Tiles tapped to find hollow spots.

    StandardBuild 1 tolerance sheetTypeTestSigned byQuality engineer
  • FN-08
    Wall tiles

    Wall tiles plumb, aligned and cut neatly at fittings.

    StandardIS 15622TypeHoldSigned bySite engineer
  • FN-09
    Stone and granite

    Thickness, polish and finish checked.

    StandardIS 14223TypeReviewSigned byQuality engineer
  • FN-10
    Stair finishes

    Riser heights uniform; nosings fixed and safe.

    StandardNBC 2016TypeHoldSigned bySite engineer
  • FN-11
    Anti-skid in wet areas

    Slip-resistant tiles used in bathrooms and outdoors.

    StandardPackage specificationTypeReviewSigned byQuality engineer

Doors and windows

  • FN-12
    Door shutters

    Shutter type, thickness and brand checked.

    StandardIS 2202 / IS 1003TypeReviewSigned byQuality engineer
  • FN-13
    Door fitting

    Shutters aligned with even gaps; swing clear.

    StandardIS 4021TypeHoldSigned bySite engineer
  • FN-14
    Hardware

    Locks, handles, hinges and stoppers fixed and working.

    StandardPackage specificationTypeSpot checkSigned bySite engineer
  • FN-15
    Windows

    Windows open, close and lock smoothly; seals in place.

    StandardIS 1948TypeHoldSigned bySite engineer
  • FN-16
    Window water test

    Windows sprayed to check for leaks.

    StandardBuild 1 tolerance sheetTypeTestSigned byQuality engineer
  • FN-17
    Glass

    Glass thickness and safety glass where required.

    StandardIS 16231TypeReviewSigned byQuality engineer
  • FN-18
    Grills and metal work

    Welds, fixing and primer checked.

    StandardIS 2629TypeHoldSigned bySite engineer

Painting

  • FN-19
    Moisture before paint

    Wall moisture measured before painting.

    StandardIS 2395TypeTestSigned byQuality engineer
  • FN-20
    Putty and primer

    Putty and primer coats applied and sanded.

    StandardIS 2395TypeSpot checkSigned bySite engineer
  • FN-21
    Paint finish

    Number of coats and evenness checked in good light.

    StandardIS 2395TypeHoldSigned byQuality engineer
  • FN-22
    External paint

    Exterior system and coats checked.

    StandardIS 2395TypeHoldSigned bySite engineer
  • FN-23
    Wood and metal finish

    Polish and enamel finishes checked.

    StandardIS 2338TypeSpot checkSigned bySite engineer

Fixtures

  • FN-24
    Sanitaryware

    Brand and model match the specification.

    StandardPackage specificationTypeReviewSigned byQuality engineer
  • FN-25
    Sanitaryware fixing

    Fixed level and sealed; no leaks.

    StandardNBC 2016 Part 9TypeHoldSigned bySite engineer
  • FN-26
    Taps and showers

    Flow and operation of every fitting tested.

    StandardNBC 2016 Part 9TypeTestSigned bySite engineer
  • FN-27
    Kitchen platform and sink

    Platform level, sink sealed, cut-outs neat.

    StandardIS 14223TypeHoldSigned bySite engineer
  • FN-28
    Drainage after fixtures

    Every fixture drained to check flow.

    StandardIS 1742TypeTestSigned byQuality engineer
  • FN-29
    False ceiling

    Frame level, joints and access panels checked, where used.

    StandardIS 2095TypeHoldSigned bySite engineer
  • FN-30
    Railings

    Height, spacing and fixing strength checked.

    StandardNBC 2016 Part 4TypeHoldSigned byQuality engineer

Electrical final

  • FN-31
    Switches and sockets

    Every point matches the layout and works.

    StandardIS 732TypeHoldSigned bySite engineer
  • FN-32
    Insulation resistance

    Every circuit tested with a megger.

    StandardIS 732TypeTestSigned byQuality engineer
  • FN-33
    Earth continuity

    Earth continuity tested to every point.

    StandardIS 3043TypeTestSigned byQuality engineer
  • FN-34
    RCCB trip test

    Every RCCB tripped to confirm it protects you.

    StandardIS 12640TypeTestSigned byQuality engineer
  • FN-35
    Polarity

    Live and neutral checked at every socket.

    StandardIS 732TypeTestSigned bySite engineer
  • FN-36
    Board labelling

    Distribution board labelled circuit by circuit.

    StandardIS 732TypeReviewSigned bySite engineer

External works

  • FN-37
    Compound wall

    Foundation, masonry and coping checked, where in scope.

    StandardIS 1905TypeHoldSigned bySite engineer
  • FN-38
    Gate

    Gate fixed, aligned and operating.

    StandardPackage specificationTypeTestSigned bySite engineer
  • FN-39
    Septic tank and soak pit

    Size, distance and watertightness checked.

    StandardIS 2470TypeHoldSigned byQuality engineer
  • FN-40
    Sump and overhead tank

    Cleaned and tested for leaks.

    StandardIS 3370TypeTestSigned byQuality engineer
  • FN-41
    Rainwater harvesting

    Filters, pipes and recharge pit checked.

    StandardIS 15797TypeHoldSigned bySite engineer
  • FN-42
    Yard drainage

    Yard slopes and drains carry water away from the house.

    StandardSite drainage planTypeHoldSigned bySite engineer
  • FN-43
    Solar plant

    Panels, inverter and earthing installed and tested, where in scope.

    StandardIS 14286, CEA regulationsTypeTestSigned byQuality engineer
  • FN-44
    Backup and systems

    Inverter, CCTV and smart-home systems commissioned, where in scope.

    StandardManufacturer specificationTypeTestSigned bySite engineer

Snags

  • FN-45
    Joint snag walk

    A snag list made together with you, room by room.

    StandardBuild 1 snag listTypeWitnessSigned byClient manager + you

Gate

  • FN-46
    Finishes gate

    Your client manager signs the finishes gate on the quality team’s records.

    StandardBuild 1 gate recordTypeHoldSigned byClient manager
G9HandoverKeys only when it’s all done14checks

Close-out

  • HO-01
    All snags closed

    Every snag fixed and checked off with photos.

    StandardBuild 1 snag listTypeHoldSigned byQuality engineer
  • HO-02
    Deep cleaning

    Home cleaned top to bottom before handover.

    StandardBuild 1 handover listTypeSpot checkSigned bySite engineer
  • HO-03
    Drinking water test

    Supply water tested before you move in.

    StandardIS 10500TypeTestSigned byNABL lab
  • HO-04
    Systems commissioned

    Pumps, heaters and every system run and handed over.

    StandardManufacturer specificationTypeTestSigned bySite engineer
  • HO-05
    Meter readings

    Electricity and water meter readings recorded.

    StandardBuild 1 handover listTypeReviewSigned bySite engineer

Documents

  • HO-06
    As-built drawings

    Drawings updated to show what was actually built.

    StandardBuild 1 handover kitTypeReviewSigned byDesign lead
  • HO-07
    Concealed services record

    Photos of every pipe and wire hidden in the walls.

    StandardBuild 1 handover kitTypeReviewSigned byQuality engineer
  • HO-08
    Test records

    Every cube, steel, pressure and ponding result in one file.

    StandardBuild 1 handover kitTypeReviewSigned byQuality engineer
  • HO-09
    Product warranties

    Warranties and manuals for every product handed over.

    StandardBuild 1 handover kitTypeReviewSigned bySite engineer
  • HO-10
    Build 1 warranty certificate

    Structural, waterproofing and defects warranty certificate.

    StandardBuild 1 agreementTypeReviewSigned byClient manager
  • HO-11
    Care guide

    How to look after the home, season by season.

    StandardBuild 1 handover kitTypeReviewSigned byDesign lead
  • HO-12
    Occupancy certificate

    Occupancy certificate applied for with the local body.

    StandardKMBR / KPBR 2019TypeReviewSigned byDesign lead

Handover

  • HO-13
    Final walkthrough

    A walk through the finished home with you.

    StandardBuild 1 handover listTypeWitnessSigned byClient manager + you
  • HO-14
    Handover certificate

    Handover certificate signed jointly; keys handed over.

    StandardBuild 1 handover listTypeWitnessSigned byClient manager + you
ACAftercareWe come back to check6checks

Aftercare

  • AC-01
    3-month visit

    We check the home and fix anything that has come up.

    StandardBuild 1 warrantyTypeWitnessSigned byQuality engineer
  • AC-02
    First monsoon check

    Terrace, walls and windows checked after the first heavy rains.

    StandardBuild 1 warrantyTypeHoldSigned byQuality engineer
  • AC-03
    6-month visit

    Second check of the home and its systems.

    StandardBuild 1 warrantyTypeWitnessSigned byQuality engineer
  • AC-04
    12-month defects inspection

    Full inspection before the defects period ends.

    StandardBuild 1 warrantyTypeWitnessSigned byQuality engineer
  • AC-05
    Defect closure

    Every reported defect fixed and signed off.

    StandardBuild 1 warrantyTypeHoldSigned byQuality engineer
  • AC-06
    Warranty register

    Your warranties tracked for their full term.

    StandardBuild 1 warrantyTypeReviewSigned byClient manager

When Build 1 also does your interiors, these 48 checks are added, from laser measurement to the final snag walk.

I1Measure and designBuilt for your exact walls8checks

Measure

  • IM-01
    Laser measurement

    Every wall, ceiling and opening measured on site with a laser.

    StandardBuild 1 measure sheetTypeHoldSigned bySite engineer
  • IM-02
    Plumb and square of walls

    Out-of-plumb walls and uneven floors recorded for the design.

    StandardBuild 1 measure sheetTypeReviewSigned bySite engineer
  • IM-03
    Services positions

    Electrical points, plumbing and windows marked on the plan.

    StandardBuild 1 measure sheetTypeReviewSigned bySite engineer

Design

  • IM-04
    Space planning

    Clearances for doors, drawers and walking space checked.

    StandardBuild 1 design rulesTypeReviewSigned byDesign lead
  • IM-05
    Kitchen work triangle

    Sink, hob and fridge placed for easy use.

    StandardBuild 1 design rulesTypeReviewSigned byDesign lead
  • IM-06
    Appliance sizes

    Cut-outs drawn from the actual appliance models.

    StandardManufacturer specificationTypeReviewSigned byDesign lead
  • IM-07
    3D views approved

    You approve the 3D views and drawings.

    StandardBuild 1 design sign-offTypeWitnessSigned byClient manager + you
  • IM-08
    Production drawings

    Factory drawings checked against the approved design.

    StandardBuild 1 drawing registerTypeReviewSigned byDesign lead
I2Materials and samplesThe boards you approved8checks

Boards

  • IA-01
    Plywood grade

    Plywood grade checked: BWP in wet areas, BWR or better elsewhere.

    StandardIS 710 / IS 303TypeReviewSigned byQuality engineer
  • IA-02
    MDF and HDHMR

    Board type, density and thickness checked, where used.

    StandardIS 12406TypeReviewSigned byQuality engineer
  • IA-03
    Laminates

    Laminate thickness, finish and shade checked.

    StandardIS 2046TypeReviewSigned byQuality engineer
  • IA-04
    Edge banding

    Edge band thickness and colour match.

    StandardBuild 1 specificationTypeReviewSigned byQuality engineer

Hardware

  • IA-05
    Hinges and channels

    Soft-close hinges and channels of the approved brand.

    StandardPackage specificationTypeReviewSigned byQuality engineer
  • IA-06
    Handles and accessories

    Handles, baskets and accessories match the approved list.

    StandardPackage specificationTypeReviewSigned byQuality engineer

Countertops

  • IA-07
    Stone or quartz

    Slab thickness, finish and colour checked.

    StandardIS 14223TypeReviewSigned byQuality engineer

Samples

  • IA-08
    Sample board approved

    You approve the board, laminate and hardware samples.

    StandardBuild 1 sample boardTypeWitnessSigned byClient manager + you
I3Factory productionChecked before it leaves7checks

Factory

  • IF-01
    Cutting accuracy

    Panels cut to size within tight tolerance.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • IF-02
    Edge banding bond

    Edges pressed, trimmed and checked for lifting.

    StandardBuild 1 tolerance sheetTypeTestSigned byQuality engineer
  • IF-03
    Drilling and hardware holes

    Hinge and dowel holes placed correctly.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • IF-04
    Surface finish

    Panels checked for scratches, chips and colour match.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • IF-05
    Dry fit

    Key units assembled in the factory before dispatch.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • IF-06
    Pre-dispatch check

    Every panel counted, labelled and checked before it leaves.

    StandardBuild 1 dispatch listTypeHoldSigned byQuality engineer
  • IF-07
    Packing

    Panels packed to avoid damage in transit.

    StandardBuild 1 dispatch listTypeSpot checkSigned bySite engineer
I4Site readinessRight room, right time5checks

Site

  • IR-01
    Civil work complete

    Plaster, flooring and first coat of paint done.

    StandardBuild 1 site-readiness ruleTypeHoldSigned bySite engineer
  • IR-02
    Walls dry

    Wall moisture measured before fixing anything.

    StandardBuild 1 site-readiness ruleTypeTestSigned byQuality engineer
  • IR-03
    Electrical and plumbing points ready

    Points in the right place and tested.

    StandardIS 732TypeHoldSigned bySite engineer
  • IR-04
    Room clean and secure

    Room cleared, protected and lockable for installation.

    StandardBuild 1 site-readiness ruleTypeSpot checkSigned bySite engineer
  • IR-05
    Delivery check

    Delivery checked against the dispatch list; damage recorded.

    StandardBuild 1 dispatch listTypeReviewSigned bySite engineer
I5InstallationFitted square and solid9checks

Installation

  • II-01
    Carcass level and plumb

    Units fixed level, plumb and square.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • II-02
    Wall fixing

    Units anchored to walls with the right fixings.

    StandardBuild 1 tolerance sheetTypeHoldSigned bySite engineer
  • II-03
    Shutter alignment

    Shutter gaps even and doors aligned.

    StandardBuild 1 tolerance sheetTypeHoldSigned byQuality engineer
  • II-04
    Hinges and channels

    Every door and drawer opened and closed to check.

    StandardManufacturer specificationTypeTestSigned bySite engineer
  • II-05
    Countertop fixing

    Countertops level with tight, sealed joints.

    StandardIS 14223TypeHoldSigned bySite engineer
  • II-06
    Sink and hob cut-outs

    Cut-outs sealed against water.

    StandardBuild 1 tolerance sheetTypeHoldSigned bySite engineer
  • II-07
    Wardrobe internals

    Shelves, rods and drawers fitted and working.

    StandardBuild 1 tolerance sheetTypeSpot checkSigned bySite engineer
  • II-08
    Wall panelling

    Panels aligned, joints tight, fixed firmly.

    StandardBuild 1 tolerance sheetTypeHoldSigned bySite engineer
  • II-09
    False ceiling

    Ceiling level with access to fittings, where in scope.

    StandardIS 2095TypeHoldSigned bySite engineer
I6Services and finishingLights, appliances, touch-ups7checks

Services

  • IS-01
    Lighting circuits

    Profile and ceiling lights tested.

    StandardIS 732TypeTestSigned bySite engineer
  • IS-02
    Appliance points

    Appliance sockets and isolators tested.

    StandardIS 732TypeTestSigned byQuality engineer
  • IS-03
    Chimney ducting

    Duct run sealed and vented outside.

    StandardManufacturer specificationTypeHoldSigned bySite engineer
  • IS-04
    Water connections

    Sink, purifier and appliance connections checked for leaks.

    StandardNBC 2016 Part 9TypeTestSigned bySite engineer

Finishing

  • IS-05
    Touch-ups

    Paint and edge touch-ups done after installation.

    StandardBuild 1 tolerance sheetTypeSpot checkSigned bySite engineer
  • IS-06
    Silicone and sealing

    Joints at walls and counters sealed neatly.

    StandardBuild 1 tolerance sheetTypeSpot checkSigned bySite engineer
  • IS-07
    Cleaning

    Units cleaned inside and out; films removed.

    StandardBuild 1 handover listTypeSpot checkSigned bySite engineer
I7HandoverSnag-free before you use it4checks

Handover

  • IH-01
    Joint snag walk

    Snag list made with you, unit by unit.

    StandardBuild 1 snag listTypeWitnessSigned byClient manager + you
  • IH-02
    Snags closed

    Every snag fixed and checked off.

    StandardBuild 1 snag listTypeHoldSigned byQuality engineer
  • IH-03
    Care guide and warranties

    How to care for each finish, with hardware warranties.

    StandardBuild 1 handover kitTypeReviewSigned bySite engineer
  • IH-04
    Handover sign-off

    You sign off the finished interiors.

    StandardBuild 1 handover listTypeWitnessSigned byClient manager + you

Standards: IS codes from the Bureau of Indian Standards, the National Building Code of India 2016 (NBC) and the Kerala building rules (KMBR / KPBR 2019). Checks marked “where used” or “where in scope” apply only when your design includes that item. Tolerances follow your package.

A quality engineer recording a check on site
You see the proof

Not just checked. Recorded for you.

  • Photos before anything is hiddenSteel before every pour, pipes and wires before plaster. You get them on your phone and in your handover kit.
  • Lab results, not promises7 kinds of test go to an accredited (NABL) lab, including soil, steel and concrete cubes at 7 and 28 days.
  • Independent sign-offOur quality engineers report to the office, not the site team. Your client manager signs every gate.
  • One file at handoverEvery check, test and photo, kept together, along with your warranty.
FAQs

About our checks.

234quality checks on every home, across ten gates.
Talk to us
Do all 234 checks really happen on my home?

Yes. A few apply only when your design has that item, like a roof truss or a solar plant, and they’re marked “where used” or “where in scope”. Checks that repeat, like the ones for every concrete pour, are done every time.

Can I see the results?

Yes. Photos and results appear on your phone as the work happens, and the full record is handed over with your keys.

What happens if a check fails?

The work is fixed and checked again before anything moves on. Hold points stop the site until they’re signed.

Can my own engineer inspect too?

Yes. You or your engineer are welcome at any check. Tell us and we’ll share the dates of the hold points.

Do interiors have their own checks?

Yes, 48 of them, from laser measurement and board grades to factory checks and installation. See the Interiors tab.

Next step

Let’s plan your home.

Every good project starts with a clear conversation. Share your plot, approximate area, requirements and budget range, and we’ll suggest the right route and package.

Free site visit and plot check

Anywhere in Thrissur and Ernakulam districts.

Your price in writing in 7 days

Itemised, within 7 days of the site visit.

See a live site on a Saturday

Walk a Build 1 site with our engineer.

None added — use “Add to my brief” in Home Solutions.
We reply within one working day.
WhatsApp usCall +91 94973 07799

We reply within one working day.

Build 1 engineer on site
Talk to our team+91 94973 07799info@build1.inBuild 1, Irinjalakuda, Thrissur, Kerala
My brief (0) →