From the land documents to the first monsoon after you move in, your home passes 234 checks across ten gates. Here is every single one: what’s checked, the standard it follows and who signs it.
Most checks sit where problems hide: the structure, then everything that disappears inside walls and floors. Tap a gate to see its checks.
Ten gates, G0 to G9, plus aftercare visits in the first year.
Every check on the list has a type and a person who signs it. Hold points are the strictest: nothing on site moves until they’re signed.
Work stops. Nothing moves on until this is checked and signed.
Done in front of you, or with you invited to see it.
Measured or tested, on site or at an accredited lab, with the result recorded.
Documents, drawings or records checked and signed.
Checked on site by surprise, as the work goes on.
Runs your site day to day and checks the work as it happens.
Reports to the office, not the site team, and signs the hold points.
Checks the brief, drawings and specification.
Your one point of contact at Build 1. Signs every gate, on the quality team’s records.
An accredited lab tests samples. Results go into your record.
Some checks need your signature too.
Search the list, or filter by type. Codes like ST-24 are how the check appears in your project record.
LD-01Ownership and the chain of title match the seller and the survey number.
LD-02No mortgage, lien or claim on the land for the period checked.
LD-03Basic tax paid up to date in the owner’s name.
LD-04Possession certificate and village location sketch match the plot on the ground.
LD-05Plot is not listed in the data bank, or the RDO order allowing a house is in hand.
LD-06CRZ map, 2018 flood levels and airport height zoning checked where they apply.
LD-07Access road width and the setbacks it triggers checked against the building rules.
LD-08Boundary stones located and plot dimensions measured against the documents.
LD-09Spot levels taken across the plot and the road to plan the plinth and drainage.
LD-10Trees, wells, structures, power lines and drains on and around the plot recorded.
LD-11Condition of neighbouring walls and buildings photographed before work starts.
LD-12Number and depth of boreholes or trial pits fixed for the soil test.
BR-01Rooms, ages, routines and future plans recorded in one brief.
BR-02Budget range and the chosen package recorded, with what each includes.
BR-03Style, materials and vastu preferences recorded with reference images.
BR-04The brief checked against plot size, setbacks and the soil and level findings.
BR-05Solar, CCTV, smart home and other systems noted so they’re designed in early.
BR-06How and when you get updates, and who else in the family gets access.
BR-07Target start and move-in dates recorded, with monsoon timing considered.
BR-08You approve the written brief before design starts.
DS-01Bearing capacity and soil type tested at an accredited lab.
DS-02Foundation type and depth designed from the soil report.
DS-03Frame, slabs and beams designed for loads and earthquake zone.
DS-04A second engineer checks the structural drawings before release.
DS-05Setbacks, coverage, floor area and height checked against the rules.
DS-06Habitable rooms, kitchens and toilets meet minimum size, light and ventilation.
DS-07Riser, tread, width and railing height meet the code.
DS-08Every opening sized and listed with its frame, shutter and glass.
DS-09Plumbing, drainage and electrical layouts coordinated with the structure.
DS-10Roof outlets, yard drainage and rainwater harvesting designed.
DS-11Septic tank and soak pit sized and placed at the required distance from wells.
DS-12Quantities taken off the drawings and cross-checked by a second person.
DS-13Every material named with brand, grade and finish.
DS-14Allowance items and exclusions listed clearly in the offer.
DS-15A dated programme, stage by stage, with monsoon allowance.
DS-16Payments linked to finished, checked stages.
DS-17Permit set prepared and signed by a licensed engineer.
DS-18Your client manager reviews price, scope and programme before you see it.
CT-01Agreement signed with all annexures attached.
CT-02Approved drawings listed by number and revision.
CT-03The specification schedule attached and initialled.
CT-04Itemised BOQ and the fixed price attached.
CT-05Dated programme and the on-time promise written in.
CT-06Structural, waterproofing and defects warranty written in.
CT-07How changes are priced and approved before work, in writing.
CT-08Daily photo updates and family access set up for you.
RS-01Permit issued by the local body and its conditions noted.
RS-02Good-for-construction drawings stamped and issued to site.
RS-03Architecture, structure and services drawings checked for clashes.
RS-04Cement, steel, blocks, pipes and wires approved by brand and grade.
RS-05Tiles, paints and fittings approved by you on a physical sample board.
RS-06Mix designed for the grade, or the ready-mix supplier approved.
RS-07NABL-accredited lab booked for cube, steel and material tests.
RS-08Windows, steel and other long-lead items ordered on time.
RS-09Site engineer, supervisor and trade teams assigned and named.
RS-10Subcontractors briefed on the checks for their work.
RS-11Programme frozen as the baseline for tracking delay.
RS-12BOQ frozen so every later change is a written variation.
RS-13Site safety plan, permits-to-work and emergency contacts ready.
RS-14Storage, access, water and power for construction planned.
RS-15Temporary water and electricity connections arranged.
RS-16Your client manager confirms the site is ready to start.
MB-01Plot and boundaries photographed and recorded at handover.
MB-02Site fenced, gated and signed; public kept safe.
MB-03A fixed benchmark set and protected for all levels.
MB-04Building lines set out from the drawings and checked by a second person.
MB-05Diagonals measured to confirm the layout is square.
MB-06Setbacks from boundaries measured against the permit drawing.
MB-07Plinth and finished floor levels fixed from the benchmark.
MB-08Every worker inducted and given a helmet, shoes and gloves.
MB-09First-aid kit on site and emergency numbers displayed.
MB-10Trench sides sloped or shored; edges barricaded.
MB-11Cement stored on a raised, dry platform and used first-in, first-out.
MB-12Brand, grade and date of manufacture checked on every delivery.
MB-13Every steel lot matched to its mill certificate and tag.
MB-14Steel samples tested at the lab for strength and elongation.
MB-15Silt content of sand checked on site before use.
MB-16Coarse aggregate size and grading checked.
MB-17Construction water tested for suitability.
MB-18Strength, size and water absorption tested on samples.
ST-01Pit or trench depth, width and level checked against the drawing.
ST-02Engineer inspects the soil at founding level before PCC.
ST-03Pits kept dry; no concrete placed in standing water.
ST-04Soil treated with approved chemical at the right dose before PCC.
ST-05Levelling concrete laid to thickness and level.
ST-06Bar size, spacing and cover in footings checked.
ST-07Starter bars positioned and held to the column grid.
ST-08Masonry foundation bond, mortar and through-stones checked, where used.
ST-09Backfill placed in layers, watered and compacted.
ST-10Bars, stirrups and laps in plinth beams checked.
ST-11Top of plinth checked against the benchmark.
ST-12DPC laid to thickness with waterproofing compound.
ST-13Filling placed in layers, compacted and treated against termites.
ST-14Shuttering aligned, levelled, plumbed and propped.
ST-15Formwork cleaned, joints sealed and release agent applied.
ST-16Bar diameter and spacing checked against the bar schedule.
ST-17Lap lengths and anchorage meet the design; laps staggered.
ST-18Cover blocks of the right size fixed throughout.
ST-19Top steel held at the right height with chairs.
ST-20Conduits, sleeves and inserts placed and photographed before the pour.
ST-21Pre-pour checklist signed and photographed before concrete arrives.
ST-22Ready-mix grade, batch time and water-cement ratio checked on the ticket.
ST-23Workability tested on arrival or at the mixer.
ST-24Cubes taken at the required frequency for every pour.
ST-25Concrete vibrated properly; no segregation.
ST-26Joints placed only where the engineer approves.
ST-27Curing started on time and logged daily for the full period.
ST-28Early strength checked at the lab.
ST-29Characteristic strength confirmed at the lab.
ST-30Props removed only after the minimum striking time.
ST-31Honeycombing, cracks and exposed steel inspected and repaired.
ST-32Main bars and ties checked, with closer ties near joints as designed.
ST-33Column size and verticality checked after stripping.
ST-34Stirrup spacing and extra bars at supports checked.
ST-35Main, distribution and extra top bars checked.
ST-36Slab depth and top level checked before and after the pour.
ST-37Wet-area sunk depth checked against the drawing.
ST-38Top reinforcement in cantilevers and sunshades checked.
ST-39Lintel bearing, size and reinforcement checked.
ST-40Waist, riser and tread checked; reinforcement continuous.
ST-41Roof slab falls to outlets; outlets sized and placed.
ST-42Non-destructive check where any concrete is in doubt.
ST-43Your client manager signs the structure gate on the quality team’s records.
EN-01Mortar mixed to the specified ratio and used within its working time.
EN-02Walls checked for line, level and plumb as they rise.
EN-03Joints even and fully filled; correct bond kept.
EN-04Ties or mesh fixed where walls meet columns.
EN-05Door and window openings sized and placed to the schedule.
EN-06Laterite blocks sound, dressed and laid to bond, where used.
EN-07Masonry kept wet for the curing period.
EN-08Frames fixed square, plumb and level with hold-fasts.
EN-09Frames protected from damage and plaster splashes.
EN-10Truss members, welds and anchorage checked, where used.
EN-11Steel cleaned and primed before painting.
EN-12Tile quality and fixing, overlap and pointing checked.
EN-13Gutters sloped and downpipes sized to carry Kerala rain.
EN-14Pipes and fittings of the approved brand and ISI grade.
EN-15Routes photographed before walls and floors are closed.
EN-16Lines held at test pressure with no drop before concealing.
EN-17Waste and soil pipes laid to the right fall.
EN-18Drain lines filled and checked for leaks.
EN-19Trap levels set so floors drain to them.
EN-20Pipes through walls and slabs sleeved and sealed.
EN-21Sump and overhead tank inlet, outlet and overflow checked.
EN-22Conduits of the right size and grade; boxes fixed level.
EN-23Conduit routes photographed before plaster.
EN-24Wire size for each circuit and colour code checked.
EN-25Circuits separated as designed; MCB and RCCB ratings checked.
EN-26Earth pits built and earth resistance measured.
EN-27TV, data, CCTV and smart-home conduits laid.
EN-28Conduits and space for solar, inverter and EV charging provided.
EN-29Air terminals and down conductors installed and tested, where specified.
EN-30Concrete hacked, surfaces wetted, mesh fixed at joints.
EN-31Mix and thickness checked against the specification.
EN-32Checked with a 2 m straightedge to the package tolerance.
EN-33Waterproofing additive and drip grooves in external plaster.
EN-34Plaster cured for the full period.
EN-35Surfaces clean, sound and coved at corners before waterproofing.
EN-36Coats applied with upturns on walls around wet areas.
EN-37Wet areas flooded and held to check for leaks.
EN-38Sunken slabs filled only after the ponding test is passed.
EN-39Terrace system laid to specification, with slopes to outlets.
EN-40Terrace flooded and held to check for leaks.
EN-41Tanks filled and checked for leaks.
EN-42Parapet tops sloped and sealed to shed water.
EN-43Every pipe through a wet area or terrace sealed.
EN-44Everything hidden in walls and floors photographed and shared.
EN-45Your client manager signs the gate on the quality team’s records.
FN-01Size, shade and batch checked before laying.
FN-02Base levelled before tiling.
FN-03Correct adhesive or bed, fully covering each tile.
FN-04Floors level; wet areas slope to the drain.
FN-05Edge height difference between tiles within the package tolerance.
FN-06Joint width even; grout full and cleaned.
FN-07Tiles tapped to find hollow spots.
FN-08Wall tiles plumb, aligned and cut neatly at fittings.
FN-09Thickness, polish and finish checked.
FN-10Riser heights uniform; nosings fixed and safe.
FN-11Slip-resistant tiles used in bathrooms and outdoors.
FN-12Shutter type, thickness and brand checked.
FN-13Shutters aligned with even gaps; swing clear.
FN-14Locks, handles, hinges and stoppers fixed and working.
FN-15Windows open, close and lock smoothly; seals in place.
FN-16Windows sprayed to check for leaks.
FN-17Glass thickness and safety glass where required.
FN-18Welds, fixing and primer checked.
FN-19Wall moisture measured before painting.
FN-20Putty and primer coats applied and sanded.
FN-21Number of coats and evenness checked in good light.
FN-22Exterior system and coats checked.
FN-23Polish and enamel finishes checked.
FN-24Brand and model match the specification.
FN-25Fixed level and sealed; no leaks.
FN-26Flow and operation of every fitting tested.
FN-27Platform level, sink sealed, cut-outs neat.
FN-28Every fixture drained to check flow.
FN-29Frame level, joints and access panels checked, where used.
FN-30Height, spacing and fixing strength checked.
FN-31Every point matches the layout and works.
FN-32Every circuit tested with a megger.
FN-33Earth continuity tested to every point.
FN-34Every RCCB tripped to confirm it protects you.
FN-35Live and neutral checked at every socket.
FN-36Distribution board labelled circuit by circuit.
FN-37Foundation, masonry and coping checked, where in scope.
FN-38Gate fixed, aligned and operating.
FN-39Size, distance and watertightness checked.
FN-40Cleaned and tested for leaks.
FN-41Filters, pipes and recharge pit checked.
FN-42Yard slopes and drains carry water away from the house.
FN-43Panels, inverter and earthing installed and tested, where in scope.
FN-44Inverter, CCTV and smart-home systems commissioned, where in scope.
FN-45A snag list made together with you, room by room.
FN-46Your client manager signs the finishes gate on the quality team’s records.
HO-01Every snag fixed and checked off with photos.
HO-02Home cleaned top to bottom before handover.
HO-03Supply water tested before you move in.
HO-04Pumps, heaters and every system run and handed over.
HO-05Electricity and water meter readings recorded.
HO-06Drawings updated to show what was actually built.
HO-07Photos of every pipe and wire hidden in the walls.
HO-08Every cube, steel, pressure and ponding result in one file.
HO-09Warranties and manuals for every product handed over.
HO-10Structural, waterproofing and defects warranty certificate.
HO-11How to look after the home, season by season.
HO-12Occupancy certificate applied for with the local body.
HO-13A walk through the finished home with you.
HO-14Handover certificate signed jointly; keys handed over.
AC-01We check the home and fix anything that has come up.
AC-02Terrace, walls and windows checked after the first heavy rains.
AC-03Second check of the home and its systems.
AC-04Full inspection before the defects period ends.
AC-05Every reported defect fixed and signed off.
AC-06Your warranties tracked for their full term.
When Build 1 also does your interiors, these 48 checks are added, from laser measurement to the final snag walk.
IM-01Every wall, ceiling and opening measured on site with a laser.
IM-02Out-of-plumb walls and uneven floors recorded for the design.
IM-03Electrical points, plumbing and windows marked on the plan.
IM-04Clearances for doors, drawers and walking space checked.
IM-05Sink, hob and fridge placed for easy use.
IM-06Cut-outs drawn from the actual appliance models.
IM-07You approve the 3D views and drawings.
IM-08Factory drawings checked against the approved design.
IA-01Plywood grade checked: BWP in wet areas, BWR or better elsewhere.
IA-02Board type, density and thickness checked, where used.
IA-03Laminate thickness, finish and shade checked.
IA-04Edge band thickness and colour match.
IA-05Soft-close hinges and channels of the approved brand.
IA-06Handles, baskets and accessories match the approved list.
IA-07Slab thickness, finish and colour checked.
IA-08You approve the board, laminate and hardware samples.
IF-01Panels cut to size within tight tolerance.
IF-02Edges pressed, trimmed and checked for lifting.
IF-03Hinge and dowel holes placed correctly.
IF-04Panels checked for scratches, chips and colour match.
IF-05Key units assembled in the factory before dispatch.
IF-06Every panel counted, labelled and checked before it leaves.
IF-07Panels packed to avoid damage in transit.
IR-01Plaster, flooring and first coat of paint done.
IR-02Wall moisture measured before fixing anything.
IR-03Points in the right place and tested.
IR-04Room cleared, protected and lockable for installation.
IR-05Delivery checked against the dispatch list; damage recorded.
II-01Units fixed level, plumb and square.
II-02Units anchored to walls with the right fixings.
II-03Shutter gaps even and doors aligned.
II-04Every door and drawer opened and closed to check.
II-05Countertops level with tight, sealed joints.
II-06Cut-outs sealed against water.
II-07Shelves, rods and drawers fitted and working.
II-08Panels aligned, joints tight, fixed firmly.
II-09Ceiling level with access to fittings, where in scope.
IS-01Profile and ceiling lights tested.
IS-02Appliance sockets and isolators tested.
IS-03Duct run sealed and vented outside.
IS-04Sink, purifier and appliance connections checked for leaks.
IS-05Paint and edge touch-ups done after installation.
IS-06Joints at walls and counters sealed neatly.
IS-07Units cleaned inside and out; films removed.
IH-01Snag list made with you, unit by unit.
IH-02Every snag fixed and checked off.
IH-03How to care for each finish, with hardware warranties.
IH-04You sign off the finished interiors.
Standards: IS codes from the Bureau of Indian Standards, the National Building Code of India 2016 (NBC) and the Kerala building rules (KMBR / KPBR 2019). Checks marked “where used” or “where in scope” apply only when your design includes that item. Tolerances follow your package.

Yes. A few apply only when your design has that item, like a roof truss or a solar plant, and they’re marked “where used” or “where in scope”. Checks that repeat, like the ones for every concrete pour, are done every time.
Yes. Photos and results appear on your phone as the work happens, and the full record is handed over with your keys.
The work is fixed and checked again before anything moves on. Hold points stop the site until they’re signed.
Yes. You or your engineer are welcome at any check. Tell us and we’ll share the dates of the hold points.
Yes, 48 of them, from laser measurement and board grades to factory checks and installation. See the Interiors tab.
Every good project starts with a clear conversation. Share your plot, approximate area, requirements and budget range, and we’ll suggest the right route and package.
Anywhere in Thrissur and Ernakulam districts.
Itemised, within 7 days of the site visit.
Walk a Build 1 site with our engineer.